An Upadate on Waste Disposal on Khandroling Building Sites

Joe Zurylo writes:

Hello to all

I received some good news from our sanitary engineer
this morning. Come to find out that the codes concerning
waste disposal on Khandroling will allow a 100% increase in use if a
composting system is used. In other words, if a particular
site is capable of sustaining a 3 bedroom house with this
alternative system it could be increased to 6 bedrooms.
This increase in usage for the composing system will be of
great benefit to us as we develop Kandroling

Monday, October 6, 2008

Building Foundation Forms




This video was taken yesterday on Sunday October 5, 2008. It shows the foundation forms are almost finished. Looking into the form one can see the reinforcing steel rods that we placed into the bedrock last week.



Just a quick up-date on what's happening over the past few weeks--

This past Monday, the footing for the colonnade was poured. we used 24 cubic yards of concrete. 9000 concrete blocks were delivered which the masons are beginning work this Thursday putting up the perimeter foundation walls. The foundation for the 12 major columns are near completion with Jim Smith and crew beginning to tie off the reinforcing steel rods. We plan to pour these large footings next week and we do mean large as some of the piers contain up to 3 cubic yards and weigh up to 12000lbs a piece. If the New England winter will hold off for another month, the foundation for the Vajra Hall will be complete.

Many Thanks to all the builders and individuals who contributed their labor and funding to the development up to this point!